Field guide · construction · November 2026

Removing a Sloped Roof to Add a Second Floor in Lakewood, Ohio — The Document Pack

Owner-builder, unpaid family labor, an Ohio PE, and the exact sheets, letters, and forms Lakewood will ask for before it lets you frame a 400 sq ft second story.

Lakewood, OH R1H 400 sq ft Nov 8, 2026

0. Assumptions and roles

This pack is for a 400 sq ft second-floor addition over an existing one-story rear wing in Lakewood, Ohio, where the existing sloped or multi-sloped roof is removed and replaced with a new floor and roof. The worked example is an R1H parcel, 50 × 175 ft, 8,750 sq ft. Substitute your address and dimensions; the document structure does not change.

Assumptions:

Role Who What they sign
Owner-builder In-laws Building permit application, homeowner affidavit, contracts, checks
Designer / PE You Architectural sheets; electrical sheets and calculations; specifications
Structural PE Ohio PE S-sheets, calculations, engineer’s letter, construction observations
ABR City of Lakewood Exterior design approval before building permit
Building Department City of Lakewood Zoning/plan review, building permit, inspections
Paid trades Registered contractors Trade permits, insurance, BWC, lien waivers
Unpaid family labor You / family No contractor registration; private acknowledgment recommended

1. The project in one paragraph

The existing one-story rear wing has a sloped or multi-sloped roof. You remove the roof covering, sheathing, rafters, and ceiling; evaluate the existing walls and foundation; install new footings, piers, beams, or columns where the engineer requires them; frame a new floor; frame new exterior walls and a new roof that ties into the existing house; and finish a 400 sq ft master bedroom and bathroom with a stair, egress window, smoke/CO alarms, electrical, plumbing, HVAC, insulation, and finishes. The footprint may not increase, but the height, rear-yard nonconformity, ABR massing, and structural load path all change.

2. The core document set

Twelve documents carry the project. The rest are supporting sheets.

# Document Who signs When What it proves
1 Pre-submittal meeting request Owner/PE Before design You asked the city the right questions
2 Zoning envelope worksheet Owner/PE Before design Height, rear yard, side yards, coverage
3 ABR project narrative + materials Owner/PE Before permit Exterior design review
4 Owner-builder affidavit Owners Permit application Owner is the GC, not a contractor
5 Unpaid family labor acknowledgment You/family Permit application No consideration; not a contractor
6 Contractor registration/insurance packet Paid subs Before work Lakewood registration, insurance, BWC
7 Plan set index + A-sheets Owner/PE Permit application Scope, dimensions, code compliance
8 Structural package (S-sheets + letter) Structural PE Permit application Existing capacity, new framing, load path
9 E/P/M/EC/LS sheets PE/trades Permit application Electrical, plumbing, HVAC, energy, life safety
10 Inspection card Owner Construction Required inspections and sequence
11 Daily log / change orders / photo log Owner/PE Construction Record of work and changes
12 Closeout binder Owner Final As-builts, warranties, permits, photos

Worked example: See the full example application with before/after plates and A/S/E/P/M/LS drawings →

3. Phase 0 — Pre-submittal

3.1 Pre-submittal email

Subject: Pre-submittal meeting — 400 sf second-floor addition over existing one-story rear wing — [ADDRESS]

To: Lakewood Division of Housing & Building / Planning & Development
From: [OWNER] / [PE]
Date: [DATE]

We are planning a 400 sq ft second-floor addition over the existing one-story rear wing at [ADDRESS], parcel [PARCEL]. The existing sloped/multi-sloped roof will be removed; a new floor and roof will be framed. The owners will act as owner-builders; [PE] will provide architectural and electrical design; an Ohio structural PE will seal the structural package.

We would like a 20-minute pre-submittal meeting to confirm:
1. Zoning: R1H height (35 ft), rear yard (40 ft), side yards (5 ft / 15 ft sum), principal footprint (35%), total coverage (85%).
2. Whether the existing rear wing is nonconforming, and whether a second story over it increases the nonconformity under LCO §1149.04.
3. ABR submission requirements and the current Architectural Standards Workbook.
4. Whether the owner-occupant may pull electrical, plumbing, and HVAC permits, or whether Lakewood requires registered specialty contractors.
5. Plan-review checklist, energy-compliance path, and whether sealed structural calculations are required.
6. Whether the parcel is in an HPD/HP or otherwise subject to Chapter 1134.

Attachments: parcel record, existing photos, zoning sketch, preliminary floor plan.

3.2 Zoning envelope worksheet

ZONING ENVELOPE WORKSHEET
Property: [ADDRESS]        Parcel: [PARCEL]        Zone: R1H
Lot: 50 ft × 175 ft = 8,750 sq ft

Item                         Existing      Proposed      Limit / Code
Principal footprint (sq ft)  [____]        [____]        3,062.5 max (35%)
Total lot coverage (sq ft)   [____]        [____]        7,437.5 max (85%)
Rear yard (ft)               [____]        [____]        40 min
Side yard left (ft)          [____]        [____]        5 min
Side yard right (ft)         [____]        [____]        5 min
Sum of side yards (ft)       [____]        [____]        15 min
Height (ft)                  [____]        [____]        35 max, per §1133.07
Front yard (ft)              [____]        [____]        Building Line Map / average

Nonconforming structure?     [ ] Yes  [ ] No
Does the addition increase
the nonconformity?           [ ] Yes  [ ] No  [ ] Unknown
ABR required?                [ ] Yes (exterior elevation change)
Historic HPD/HP?             [ ] Yes  [ ] No  [ ] Unknown
BZA variance required?       [ ] Yes  [ ] No  [ ] Unknown

3.3 Existing conditions narrative

EXISTING CONDITIONS — NARRATIVE

The existing one-story rear wing is [dimensions] with a [gable/hip/shed/multi-slope] roof. Roof covering is [material]; sheathing is [material]; rafters are [size/spacing]; ceiling joists are [size/spacing]; walls are [framing/masonry]; foundation is [type/depth/condition]. The wing sits [__] ft from the rear lot line and [__] ft from each side lot line.

The roof has [number] slopes and [number] valleys/ridges. The new floor framing must transfer load to existing walls or new beams/columns. The existing roof removal will expose the wall tops; temporary shoring is required before any structural member is cut.

Photographs: [list]. Measurements: [attach]. Prior permits: [list]. Lead/asbestos: [test results or “to be tested before demo”].

3.4 Code matrix

CODE MATRIX — RESIDENTIAL ADDITION

Code / edition                     Applies to                  Evidence
2019 Residential Code of Ohio      1–3 family dwelling         Plan sheets, details
2023 NEC (Ohio, eff. 4/15/2024)    Electrical                  E-sheets, load calc
Ohio Plumbing Code (current)       Plumbing                    P-sheets, riser
2018 IECC (as referenced by RCO)   Energy                      EC-sheet
Lakewood Ch. 1121                  Zoning envelope             Zoning worksheet
Lakewood Ch. 1133.07               Height measurement           Elevations/sections
Lakewood Ch. 1149                  Nonconformities             Zoning letter
Lakewood Ch. 1325                  ABR                         ABR approval
Lakewood Ch. 1323                  Contractor registration     Registration packet

4. Phase 1 — Zoning and ABR

4.1 Zoning/ABR cover letter

[DATE]

City of Lakewood
Division of Housing & Building
12650 Detroit Avenue
Lakewood, OH 44107

Re: Zoning/ABR application — 400 sq ft second-floor addition
Property: [ADDRESS], parcel [PARCEL], R1H

To the Building Commissioner and Architectural Board of Review:

The owners, [OWNER NAMES], propose to remove the existing sloped/multi-sloped roof over the one-story rear wing and construct a 400 sq ft second-floor addition with a new roof. The first-floor footprint will not change. The addition contains [bedroom/bath/closet/stair]. The proposed height is [__] ft; the rear yard is [__] ft; side yards are [__] and [__] ft.

The existing rear wing is [conforming / nonconforming] as to the 40-ft rear yard. [If nonconforming: The addition is directly above the existing footprint and does not extend the footprint; the owners request the City’s written determination whether this increases the nonconformity under LCO §1149.04.] [If a variance is required: A BZA variance application is included.]

The project is subject to ABR review because it alters exterior elevations. The design uses [siding], [roofing], [windows], [trim], and [colors] to match the existing house and the block. No front elevation change is proposed except [describe].

Attachments: zoning worksheet, existing/proposed plans, elevations, materials board, photos.

Respectfully,
[OWNER] / [PE]

4.2 ABR project narrative

ABR PROJECT NARRATIVE

Project: 400 sq ft second-floor addition over existing one-story rear wing
Address: [ADDRESS]
Owner: [OWNER]
Designer: [PE], Ohio PE [LICENSE NO.]

Existing conditions: [one-story rear wing; roof form; materials; colors; windows; adjacent houses].

Proposed design:
- Remove the existing sloped/multi-sloped roof.
- New second-floor volume set within the existing first-floor footprint.
- New roof form: [gable/hip] with [__] pitch, tying into the existing [ridge/valley/wall].
- Exterior materials: [siding], [roofing], [windows], [trim], [gutters].
- Colors: [body], [trim], [roof].
- Windows: [style/size/location]; bedroom egress window on [elevation].
- Height: [__] ft; rear yard: [__] ft; side yards: [__]/[__] ft.
- No new lot coverage; no front-yard change.

Compatibility: The massing steps back from the existing ridge; the roof pitch and materials match the existing house; window rhythm aligns with [adjacent/neighboring]; the addition is subordinate to the main house.

Photos: [front/side/rear/context].

4.3 ABR materials board

MATERIALS / COLORS

Siding: [manufacturer, profile, color]
Roofing: [manufacturer, profile, color]
Windows: [manufacturer, material, color, grid]
Trim: [material, size, color]
Gutters/downspouts: [material, color]
Foundation exposure: [material/color]
Lighting: [fixture style/color]
Doors: [material/color]

Samples: [attach manufacturer chips/photos].

4.4 Variance narrative

Use only if the zoning officer says the second story increases a rear-yard or height nonconformity.

BZA VARIANCE NARRATIVE

Property: [ADDRESS], parcel [PARCEL], R1H
Request: [rear-yard / height] variance for a 400 sq ft second-floor addition over an existing one-story rear wing.

Existing condition: The one-story rear wing is [__] ft from the rear lot line; the R1H minimum is 40 ft. The wing was [built/expanded] in [year] and is [lawful nonconforming / conforming].

Proposal: The second floor is directly above the existing footprint. It does not extend the footprint, does not add lot coverage, and does not move the rear wall. [If true: The addition actually reduces the visual bulk by replacing the existing roof with a [lower/higher] roof.]

Hardship: [describe the practical difficulty: existing foundation/wall layout, stair location, structural feasibility, no feasible conforming location, etc. Do not claim financial hardship alone.]

No increase in nonconformity: [Explain why the addition does not increase the nonconformity: same footprint, same rear wall, same side walls, height within limit, etc.] [If it does increase: explain why the variance is necessary and why the relief is minimal.]

Neighborhood: [describe surrounding houses, setbacks, heights].

4.5 Historic/HP narrative

HISTORIC PRESERVATION NARRATIVE

Property: [ADDRESS]
Status: [HPD / HP / not designated / unknown]

The proposed addition removes the existing rear roof and constructs a second-floor volume within the existing footprint. The front elevation is [unchanged / changed only by ___]. Materials and roof form are [compatible with the historic character]. No historic fabric is removed on the front elevation. [Describe any distinctive features and how they are protected.]

Attachments: photos, elevations, materials, Secretary of the Interior Standards compliance statement.

5. Phase 2 — Owner-builder and labor

5.1 Owner-builder affidavit

Use Lakewood’s current form; this is the substance.

OWNER-BUILDER AFFIDAVIT

I, [OWNER], am the owner of record of [ADDRESS], parcel [PARCEL]. I will act as my own general contractor for the construction of a 400 sq ft second-floor addition. I understand that I am responsible for:
- obtaining all required permits;
- scheduling all required inspections;
- ensuring the work complies with the 2019 RCO, 2023 NEC, Ohio Plumbing Code, 2018 IECC, and Lakewood ordinances;
- using only registered contractors for paid work;
- maintaining insurance and workers’ compensation for paid labor;
- protecting the public and the workers on the site.

I will not allow any paid contractor to work without Lakewood contractor registration and the required insurance/BWC certificates. I will not conceal work before inspection.

Owner: ______________________  Date: __________
Co-owner: ____________________  Date: __________
Notary: ______________________

5.2 Unpaid family labor acknowledgment

This is a private record, not a city form. It is evidence that you are not a contractor under LCO §1323.01.

UNPAID FAMILY LABOR ACKNOWLEDGMENT

I, [NAME], am assisting [OWNER] with the construction of a second-floor addition at [ADDRESS] as unpaid family labor. I am not receiving wages, fees, profit, or other consideration for this work. I am not acting as a contractor or holding myself out as a contractor.

I understand that if I receive compensation for this work, I must comply with Lakewood contractor registration (LCO Ch. 1323) and any applicable trade registration.

Worker: ______________________  Date: __________
Owner: _______________________  Date: __________

5.3 Contractor registration / insurance checklist

PAID CONTRACTOR PACKET — CHECKLIST

[ ] Lakewood contractor registration (annual)
[ ] Certificate of general liability insurance
[ ] Certificate of workers’ compensation (BWC) or owner exemption
[ ] State trade license (if applicable)
[ ] Lead-safe RRP certification (pre-1978 housing; paid work)
[ ] W-9
[ ] Written contract / scope / schedule
[ ] Permit responsibility (who pulls the trade permit)
[ ] Lien waiver at each payment
[ ] Warranty / call-back terms
[ ] Site safety / debris / cleanup

5.4 Subcontractor agreement

SUBCONTRACTOR AGREEMENT — SHORT FORM

Project: 400 sq ft second-floor addition, [ADDRESS]
Owner: [OWNER]
Subcontractor: [NAME], Lakewood registration [NO.]
Scope: [electrical / plumbing / HVAC / roofing / insulation / drywall / concrete]
Contract sum: $[____]
Schedule: [start] to [finish]
Permits: [subcontractor / owner] pulls [trade] permit
Insurance: general liability $[____]; BWC [attached]
Lead/asbestos: [RRP cert attached / not applicable]
Payment: [progress payments]; lien waiver required with each payment
Change orders: written, signed by owner and subcontractor before work
Warranty: [__] months on workmanship
Cleanup: daily; dumpster [owner/sub]
Safety: subcontractor responsible for its crew and OSHA compliance
Dispute: [county/venue]
Signatures: ______________________  Date: __________

5.5 Lien waiver

CONDITIONAL PROGRESS / FINAL LIEN WAIVER

Project: [ADDRESS]
Subcontractor: [NAME]
Through date: [DATE]
Amount paid: $[____]

The undersigned, for itself and its subcontractors/suppliers, waives and releases all liens and claims against the property for labor, materials, or services furnished through the date above, to the extent of the amount paid. This waiver is conditional on receipt of the stated payment.

Signed: ______________________  Date: __________

6. Phase 3 — Permit plan set

6.1 Plan set index

SHEET INDEX

A0.0   Cover / general notes / code matrix
A1.0   Existing conditions and demolition plan
A2.0   Proposed second-floor plan
A3.0   Exterior elevations
A4.0   Building sections
A5.0   Roof plan and roof/wall details
A6.0   Stair, guard, handrail, and egress details
S1.0   Foundation plan and details
S2.0   Floor/roof framing plan
S3.0   Structural details and connections
S4.0   Structural calculations (sealed)
E1.0   Electrical plan
E2.0   Electrical load calculation and panel schedule
P1.0   Plumbing plan and riser
M1.0   HVAC plan, Manual J, duct schedule
EC1.0  Energy code compliance
LS1.0  Life safety, egress, smoke/CO

6.2 A0.0 cover and general notes

A0.0 — COVER / GENERAL NOTES

Project: 400 sq ft second-floor addition over existing one-story rear wing
Address: [ADDRESS]
Owner: [OWNER]
Designer: [PE], Ohio PE [LICENSE NO.]
Structural PE: [NAME], Ohio PE [LICENSE NO.]
Code: 2019 Residential Code of Ohio; 2023 NEC; current Ohio Plumbing Code; 2018 IECC; Lakewood Chs. 1121, 1133, 1149, 1301, 1323, 1325.
Occupancy: one-family dwelling.
Scope: remove existing sloped/multi-sloped roof; construct new floor, walls, roof, stair, bedroom, bathroom; new electrical, plumbing, HVAC; insulation and finishes.
Permit: do not start work before permit issuance. Do not cover work before inspection.
ABR: approval attached.
Notes: [abbreviations, keynotes, north arrow, scale, date].

6.3 A1.0 existing/demolition plan

A1.0 — EXISTING / DEMOLITION NOTES

1. Verify all dimensions before demolition. Report discrepancies to the designer.
2. Protect the first floor from water and debris.
3. Install temporary shoring per S3.0 before removing any roof or wall member.
4. Remove existing roof covering, sheathing, rafters, ceiling, and insulation over the one-story rear wing.
5. Salvage [items]. Disconnect [electrical/plumbing/HVAC] per trade permits.
6. Test for lead paint and asbestos before disturbance. Use RRP/lead-safe practices where required.
7. Provide temporary weather protection; do not leave the building open overnight.
8. Remove debris per Lakewood requirements; no burning.

6.4 A2.0 proposed second-floor plan

A2.0 — PROPOSED SECOND FLOOR

Room schedule:
- Bedroom: [__] ft × [__] ft = [__] sq ft
- Bathroom: [__] ft × [__] ft = [__] sq ft
- Closet: [__] ft × [__] ft = [__] sq ft
- Stair/hall: [__] sq ft
- Total: 400 sq ft

Notes:
1. Ceiling height: 7 ft minimum for habitable space; 50% of room at 7 ft; 5 ft minimum at edges.
2. Bathroom ceiling: 6 ft 8 in minimum.
3. Bedroom emergency escape opening: 5.7 sq ft, 24 in min height, 20 in min width, sill ≤44 in.
4. Smoke alarms: interconnected, each bedroom, outside sleeping area, each story.
5. CO alarms: near bedrooms.
6. Stair: 36 in clear width; 10 in tread; 7-3/4 in max riser; 6 ft 8 in headroom; handrail 34–38 in; guard 36 in.
7. Door widths: [__].
8. Show all dimensions, wall types, window/door tags, and finishes.

6.5 A3.0 elevations and sections

A3.0 — ELEVATIONS / SECTIONS

Show:
- Existing and proposed grade.
- Existing house outline and new addition.
- Roof form, pitch, ridges, valleys, eaves, overhangs.
- Height from mean curb level to mean roof height; confirm ≤35 ft.
- Windows, doors, siding, trim, gutters, downspouts.
- Wall section: siding, sheathing, framing, insulation, drywall, vapor/air barrier.
- Roof section: roofing, underlayment, ice barrier, sheathing, framing, insulation, ventilation.
- Floor section: finish, subfloor, joists, insulation, ceiling.
- Stair section: risers, treads, headroom, guard, handrail.

6.6 A5.0 roof plan and details

A5.0 — ROOF PLAN / DETAILS

1. Show all roof slopes, ridges, valleys, hips, eaves, and crickets.
2. Show how the new roof ties into the existing roof/wall at [locations].
3. Ice barrier: required at eaves; extend [__] ft.
4. Underlayment: [spec].
5. Flashing: step flashing, counterflashing, valley flashing, kick-out flashing.
6. Ventilation: ridge vent, soffit vent, baffles; calculate net free area.
7. Gutters/downspouts: size, location, discharge.
8. Multi-slope tie-in details: [drawing references].

6.7 LS1.0 life safety and egress

LS1.0 — LIFE SAFETY / EGRESS

[ ] Bedroom emergency escape opening: 5.7 sq ft; 24 in min height; 20 in min width; sill ≤44 in.
[ ] Stair: 36 in clear width; 10 in tread; 7-3/4 in max riser; 6 ft 8 in headroom.
[ ] Landing at top/bottom; door swing does not reduce width.
[ ] Guard: 36 in min at stair/landing; balusters ≤4 in.
[ ] Handrail: 34–38 in; continuous; graspable.
[ ] Smoke alarms: interconnected; bedroom, outside sleeping area, each story.
[ ] CO alarms: near bedrooms.
[ ] Hallway/landing lighting.

7. Phase 4 — Structural package

7.1 Structural engineer letter

[STRUCTURAL PE LETTERHEAD]

[DATE]

City of Lakewood
Division of Housing & Building
12650 Detroit Avenue
Lakewood, OH 44107

Re: Structural review — 400 sq ft second-floor addition
Property: [ADDRESS], parcel [PARCEL]

To the Building Commissioner:

I have reviewed the existing one-story rear wing and the proposed second-floor addition. The existing foundation is [type/condition]; the existing walls are [type/condition]; the existing roof framing is [type/condition]. Based on [visual review / destructive exploration / calculations], the existing structure [is / is not] capable of supporting the proposed loads without the modifications shown on S1.0–S3.0.

The proposed design includes [new footings/piers], [new beam], [new columns], [new floor framing], [new roof framing], [shear walls/hold-downs], and [connections]. The design complies with the 2019 RCO and accepted structural practice for the loads shown in S4.0.

Required construction observations:
1. Foundation/footing inspection before concrete.
2. Framing inspection before covering.
3. Final structural observation.

[Special inspections / shoring requirements.]

Seal:
[NAME], Ohio PE [LICENSE NO.]

7.2 S1.0 foundation notes

S1.0 — FOUNDATION PLAN / NOTES

1. New footings/piers at [locations]; size [__]; depth below frost [__]; bearing [__] psf assumed.
2. New beam: [size/material]; span [__]; bearing [__].
3. New columns: [size/material]; base/cap connections.
4. Existing foundation: [verify/underpin/leave]; engineer to observe.
5. Waterproofing/drainage: [detail].
6. Backfill/compaction: [spec].
7. Inspection: footing/foundation before concrete.

7.3 S2.0 framing notes

S2.0 — FLOOR / ROOF FRAMING

1. New floor joists: [size/spacing/species/grade]; span [__]; bearing [__].
2. New beam: [size/material]; span [__]; deflection [__].
3. New headers: [size]; span [__].
4. Roof framing: [rafters/trusses]; spacing [__]; connections.
5. Shear walls: [locations]; sheathing [__]; nailing [__]; hold-downs [__].
6. Floor/roof diaphragms: [sheathing/nailing].
7. Connections: joist hangers, ledger, beam/column, roof-to-wall, floor-to-wall.
8. Load path: roof → walls → floor → beam/columns → foundation.

7.4 S3.0 details list

S3.0 — DETAILS

- Beam-to-column connection
- Column base/cap
- Joist hanger at beam/ledger
- New floor-to-existing wall
- New roof-to-existing wall/ridge
- Shear-wall hold-down
- Stair stringer/landing
- Guard/handrail
- Temporary shoring detail

7.5 S4.0 calculation cover

S4.0 — STRUCTURAL CALCULATIONS

Design criteria:
- Dead loads: [roof/floor/walls]
- Live loads: [40 psf floor / 20 psf roof / 30 psf snow? confirm local]
- Wind: 115 mph ultimate (RCO Table 301.2(1)); exposure [__]
- Seismic: [local SDC]
- Deflection: [L/360 floor; L/240 roof? confirm]
- Existing framing: [species/grade/size/spacing/condition]
- New members: [sizes/grades]
- Connections: [capacities]
- Software/assumptions: [__]
- Limitations: [concealed conditions, field verify]
Seal: [NAME], Ohio PE [LICENSE NO.]

7.6 Shoring and roof-removal sequence

ROOF REMOVAL / SHORING SEQUENCE

1. Install temporary shoring per S3.0. Do not cut or remove any structural member before shoring is in place.
2. Protect the first floor; install temporary weather protection.
3. Remove roof covering, sheathing, rafters, and ceiling only in the sequence shown.
4. Inspect existing wall/framing conditions; notify the structural PE if conditions differ.
5. Install new foundation/beam/columns.
6. Frame new floor; connect to existing walls per details.
7. Frame new walls and roof; tie into existing ridge/valley/wall.
8. Dry-in the roof before removing temporary weather protection.
9. Remove shoring only after the structural PE approves the completed connections.
10. Schedule framing inspection before covering any work.

8. Phase 5 — Electrical, plumbing, HVAC, energy

8.1 E1.0 electrical plan notes

E1.0 — ELECTRICAL

Code: 2023 NEC as amended by Ohio (OAC 4101:8-34-01, effective 4/15/2024).
1. New 20A bathroom circuit; GFCI protection.
2. AFCI protection for bedroom/living circuits.
3. Receptacles: [spacing/locations]; bedroom, bath, hall.
4. Lighting: [fixtures]; switched at doors; bathroom exhaust.
5. Smoke/CO: interconnected; locations per LS1.0.
6. Panel: [existing/new subpanel]; load calculation E2.0.
7. Grounding/bonding: [verify].
8. Surge protection: [where provided / per Ohio amendment].

8.2 E2.0 load calculation and panel schedule

E2.0 — LOAD CALCULATION

General lighting: [__] sq ft × 3 VA = [__] VA
Small appliance: 2 × 1,500 VA = 3,000 VA
Laundry: 1,500 VA
Bathroom: 1,500 VA
Bedroom receptacles: [__]
HVAC: [__] VA
Water heater: [__] VA
Range/dryer: [__]
Total demand: [__] VA
Service: [__] A, [__] V
Existing load: [__]
New load: [__]
Panel capacity: [__]

PANEL SCHEDULE
Circuit | Description | Amps | AFCI/GFCI | Wire | Notes
[__]    | Bedroom     | 15/20| AFCI      | 14/12| [__]
[__]    | Bath        | 20   | GFCI      | 12   | [__]
[__]    | Smoke/CO    | 15   | AFCI      | 14   | [__]

8.3 P1.0 plumbing notes

P1.0 — PLUMBING

Code: current Ohio Plumbing Code.
Fixtures: water closet, lavatory, shower/tub.
Drain: 3 in WC; 1-1/2 in lav; 2 in shower; slope 1/4 in/ft.
Vent: [__] in; connect to existing vent per code; [__] ft developed length.
Water: [__] in supply; [__] psi; shutoff/access.
Cleanout: [location].
Freeze protection: [insulation/heat trace].
Access panels: [locations].

8.4 M1.0 HVAC notes

M1.0 — HVAC

1. Manual J room-by-room load calculation attached.
2. Equipment: [model/capacity]; [heat/cool].
3. Duct design: [supply/return sizes]; [R-value]; [sealing].
4. Return air: [path].
5. Bath exhaust: [CFM]; [duct size]; [termination].
6. Fresh air: [strategy].
7. Condensate: [drain].
8. Combustion air: [if applicable].

8.5 EC1.0 energy code

EC1.0 — ENERGY CODE

Code: 2018 IECC as referenced by the 2019 RCO.
Ceiling/roof: R-[__]
Walls: R-[__]
Floor: R-[__]
Windows: U-[__], SHGC-[__]
Doors: U-[__]
Air sealing: [details]
Duct sealing: [mastic/tape]
Ventilation: [bath/kitchen]
Compliance path: [prescriptive / REScheck]

9. Phase 6 — Permit submission

9.1 Building permit application fields

BUILDING PERMIT APPLICATION — KEY FIELDS

Owner: [OWNER]
Address: [ADDRESS]
Parcel: [PARCEL]
Scope: second-floor addition over existing one-story rear wing; remove existing roof; new floor/roof; bedroom/bath; electrical/plumbing/HVAC.
Occupancy: one-family dwelling.
Construction type: [wood frame / masonry / mixed].
Valuation: $[____] (materials + paid labor; owner labor may be excluded per city policy — confirm).
Designer: [PE], Ohio PE [LICENSE NO.]
Structural PE: [NAME], Ohio PE [LICENSE NO.]
Contractor: Owner-builder (see affidavit)
ABR approval: [date/attached]
Historic: [yes/no/attached]
Flood: [yes/no]
Energy: [attached]

9.2 Submittal checklist

PERMIT SUBMITTAL CHECKLIST

[ ] Building permit application (signed by owner)
[ ] Owner-builder affidavit
[ ] Unpaid family labor acknowledgment (recommended)
[ ] Contractor registration/insurance (paid subs)
[ ] Zoning envelope worksheet
[ ] ABR approval letter
[ ] BZA variance approval (if applicable)
[ ] Historic/HP approval (if applicable)
[ ] Plan set A0–LS1
[ ] Structural calculations (sealed)
[ ] Electrical load calculation/panel schedule
[ ] Plumbing riser
[ ] HVAC Manual J/duct layout
[ ] Energy compliance
[ ] Survey/site plan
[ ] Fees

9.3 Fee/valuation worksheet

VALUATION WORKSHEET

Design/engineering: $[____]
Permits/fees: $[____]
Foundation: $[____]
Framing: $[____]
Roofing: $[____]
Windows/siding: $[____]
Electrical: $[____]
Plumbing: $[____]
HVAC: $[____]
Insulation/drywall: $[____]
Finishes: $[____]
Contingency 20–30%: $[____]
Total: $[____]

10. Phase 7 — Construction and inspections

10.1 Inspection card

INSPECTION CARD

[ ] Pre-construction / permit posting
[ ] Footing/foundation before concrete
[ ] Foundation/waterproofing
[ ] Framing (floor, walls, roof, stair, shear/hold-downs)
[ ] Electrical rough-in
[ ] Plumbing rough-in
[ ] HVAC rough-in
[ ] Insulation/air sealing
[ ] Drywall (before finish)
[ ] Final building
[ ] Final electrical
[ ] Final plumbing
[ ] Final HVAC
[ ] Smoke/CO
[ ] ABR final (if required)

10.2 Daily log

DAILY LOG

Date: [DATE]
Weather: [__]
Crew: [names/trades]
Work completed: [__]
Inspections: [__]
Deliveries: [__]
Issues/delays: [__]
Photos: [numbers]
Safety: [__]

10.3 Change order

CHANGE ORDER

Project: [ADDRESS]
Change: [describe]
Reason: [field condition / owner request / code]
Cost: $[____]
Schedule impact: [__] days
Approved by owner: __________________  Date: ______
Contractor: _________________________  Date: ______

10.4 Photo log

PHOTO LOG

[Date] [Location] [Description] [Before/During/After]
[__]   [__]       [__]          [__]

11. Phase 8 — Closeout

11.1 As-built cover

AS-BUILT COVER

Project: [ADDRESS]
Permit: [__]
Scope: 400 sq ft second-floor addition; roof removal; new floor/roof; MEP; finishes.
Changes from permit: [list / none]
Attachments: as-built plans, inspection records, warranties, photos, lien waivers.
Owner: [OWNER]
Date: [DATE]

11.2 Final inspection checklist

FINAL INSPECTION CHECKLIST

[ ] All permits signed off
[ ] Smoke/CO alarms tested
[ ] Egress window operates
[ ] Stair/guard/handrail secure
[ ] GFCI/AFCI tested
[ ] Plumbing fixtures operate; no leaks
[ ] HVAC operates; filters installed
[ ] Insulation/air sealing complete
[ ] Exterior flashing/siding/roof complete
[ ] Site cleaned; debris removed
[ ] As-builts/warranties delivered

11.3 Warranty and records

WARRANTY / RECORDS

Roof: [__] years
Siding: [__]
Windows: [__]
Electrical: [__]
Plumbing: [__]
HVAC: [__]
Workmanship: [__]
Maintenance: [gutters, filters, caulk, paint]

12. Schedule and budget templates

12.1 16-week schedule

WEEK  ACTIVITY
1     Pre-submittal; measure; order survey
2-3   Structural evaluation; zoning determination
3-5   Architectural/structural/MEP design
5-6   ABR submission; plan review
6-8   Permit issuance; material ordering
8-9   Shoring; roof removal; temporary dry-in
9-10  Foundation; inspection
10-12 Framing; roof; inspection
12-13 Windows/siding; roof dry-in
13-14 Electrical/plumbing/HVAC rough; inspections
14-15 Insulation; drywall
15-16 Finishes; final inspections; closeout

12.2 Budget categories

Design/engineering
Permits/fees
Survey
Temporary shoring/weather
Foundation
Framing/lumber
Roofing
Windows/doors
Siding/trim
Electrical
Plumbing
HVAC
Insulation/drywall
Finishes
Equipment rental/dumpster
Contingency 20–30%

12.3 Contingency rules

13. What not to do

  1. Do not start demolition before the building permit is issued.
  2. Do not remove the roof before shoring and temporary weather protection are in place.
  3. Do not cover framing, electrical, plumbing, or HVAC before inspection.
  4. Do not pay an unregistered contractor or one without insurance/BWC.
  5. Do not disturb lead paint or asbestos without testing and the required certifications.
  6. Do not assume “over the existing footprint” solves the rear-yard nonconformity. Get the zoning officer’s written determination.
  7. Do not exceed 35 ft or the 40-ft rear yard without a variance.
  8. Do not use your Delaware PE seal on Ohio documents. Use your Ohio PE, or a local Ohio PE.
  9. Do not seal structural work outside your competence. Use a structural PE and document peer review.
  10. Do not promise clients “we sign anything.” Scope the service line.

14. Caveats

These are templates, not sealed documents. Lakewood’s forms, plan-review checklist, and ABR requirements can change. The code editions referenced here are the 2019 RCO, 2023 NEC (Ohio effective 4/15/2024), the current Ohio Plumbing Code, and the 2018 IECC as referenced by the RCO; verify the current editions with the Building Department. The zoning numbers are for R1H: 35 ft height, 40 ft rear, 5 ft side / 15 ft sum, 35% principal footprint, 85% total coverage. A variance, historic review, or structural condition can change the path.

15. Sources